Capital Project

 RENEWAL PROJECT
 UPDATE MARCH 2, 2020: Major progress made
 Pic of New music room at IHS
 
  • IHS Music Room: Winter Recess (Feb. 17-21) allowed Campus Construction to make major strides in completing half of the new music room at Irondequoit HS. The original (larger) room was split into two by a wall. The other half is nearing completion. 
 New bathroom at Dake Jr. HS
 
  • Bathrooms at Dake: This is a picture of a renovated, second-floor bathroom of Dake Junior High School. New toilets and stalls were also installed on the opposite of the room. Bathrooms are also being renovated at IHS.  
 UPDATE FEB. 11, 2020: Bathrooms at Dake/IHS
 Picture of bathroom at Dake
 
  • Bathrooms: Framing of walls in bathrooms at Irondequoit High School has been done along with the installation of floor and wall tiles (pictured above) at Dake Junior High School. Piping and electrical work also has been completed.
  • Music room: Drywall work and painting was done in the music room at IHS. Installation of the floor in this room is scheduled for this week.
 UPDATE FEB. 3, 2020: Music Room update
 Photo of music room under construction
  •  Music Room: Plenty of progress has been made on the permanent wall being built to divide the music room at Irondequoit High School (see picture above). The door leading outside to the front of IHS also is being removed and becoming a wall.
  • Nurse's Office at IHS: Work is being done to add a new entrance to the Nurse's Office from the front hallway. Students will no longer need to enter the front vestibule leading out of the building to enter the Nurse's Office. 
 
UPDATE JAN. 16, 2020: Work at IHS
 Picture of outside IHS
  • Among renovations being done at Irondequoit High School is a permanent wall to divide the music room. That will mean the removal of the door. Here workers are creating a temporary frame so the work on the door can be done during snowy weather.
 UPDATE JAN. 10, 2020: IHS renovations progress
  • Work at IHS that started over holiday break is progressing in January. That has included removing fixtures, partitions and accessories in multiple bathrooms, electrical work in the tech room/shop and a temporary repair of the roof over the tech wing. Roof replacement in that area is scheduled to happen once the weather breaks in a few months. Renovations in the IHS music room also are underway.
 UPDATE DEC. 19, 2019: Work at IHS over break
 Photo of IHS sign in front of building

  • Bathroom renovation work is scheduled happen over holiday break at Irondequoit High School. The first step is minor abatement above the existing ceilings of the second- and third-floor bathrooms. Work is expected to be completed before students return for classes on Jan. 6, 2020. Similar renovations on two other bathroom areas are scheduled for the upcoming months. Those dates are not set. More information will be provided when they are. As per NYS Dept. of Environmental Conservation regulations for abatement, signs have been posted. Certified abatement contractors will handle the work and follow all DEC regulations. 
UPDATE DEC. 11, 2019: The Listwood School playground is open for play! 
 Pic of completed Listwood playground

 
  • Listwood: Despite challenging weather recently, work has been completed on the new playground at Listwood elementary. Children will be playing on it soon!
  • IHS roof: As a result of the winter weather, the first phase of roof replacement work at Irondequoit High School has been rescheduled for the spring.
UPDATE NOV. 7, 2019: Listwood playground work underway; IHS roof work scheduled to start next week

Photo of Listwood playground under construction
  • Listwood: The playground at Listwood School closed Nov. 5 and construction is underway.  
  • Irondequoit HS: Roof replacement at IHS is expected to start soon above the Tech wing at the back of Irondequoit High School. That will close several parking spaces adjacent to the entrance. Staff/visitors may park in the lot behind the stadium scoreboard, near the tennis courts. See below. Work should not impact traffic flow.
 Construction map of IHS

UPDATE OCT. 25, 2019: Listwood playground work to start soon; updates on roof work at Rogers/IHS 
 
Rendering of new Listwood playground

  •  Listwood: The playground at Listwood School is scheduled to close in early November as construction begins to make it the fourth playground in the District this year to be updated with new equipment. 
  • Rogers/IHS roof updates: The roof replacement at Rogers Middle School is scheduled to finish the week of October 28th, weather pending. After that is complete, work is scheduled to shift to replacing the roof above the Tech wing at the back of Irondequoit High School. That is expected to start in early November.
 UPDATE OCT. 6, 2019: Seneca playground opens
 
Picture of completed Seneca playground

After being relocated to an area near the school that gives staff better visibility, the Seneca playground re-opened on Saturday, Oct. 5!

 UPDATE SEPT. 24, 2019: Rogers roof repair
Picture of Rogers School
Work is scheduled to begin in October at Rogers Middle School by Elmer W. Davis Roofing and Campus Construction. It will replace part of the roof.  The first step is an abatement. The majority of the abatement entails removing hazardous material due to pigeons nesting in an isolated area. In addition, a minimal amount of asbestos must be removed. The only abatement being done is to the exterior of the building and there is no airborne danger. None of the work is above any classrooms. 

For more details, click here.

 UPDATE AUG. 30, 2019: Two playgrounds completed
Picture of completed Briarwood Playground

 

Picture of completed Brookview playground

  • Briarwood: Redone and ready for play!
  • Brookview: Redone and ready for play!
  • Seneca: The playground area is fenced off and construction is under way. It should be completed in September.

Please stay off the newly planted grass seed.

 UPDATE AUG. 21, 2019: Construction update
Brookview playground 
  • Briarwood: Equipment is in place and chips have been spread.
  • Brookview: Equipment is in place and chips are being spread.
  • Seneca: The playground area is fenced off and the process of clearing is under way. 

Picture of Briarwood Playground on Aug. 9, 2019
UPDATE AUG. 9, 2019: Construction update
  • Briarwood: Equipment is in place and chips are being spread throughout the area.
  •  Brookview: The playground area is fenced off and the process of clearing is under way.
  • Seneca: Work has not started yet. 
 Picture of construction at Briarwood playground
UPDATE JULY 18, 2019: Construction has started on our playgrounds project.
  •  Briarwood: Work is underway to make the necessary changes to the playground.
  •  Brookview: The playground area is fenced off. Work will begin soon.
  • Seneca: Work has not started yet.
UPDATE JUNE 3, 2019: The first phase of our Renewal Project, which was passed in our 2018-19 District vote, has begun. Itune 2019 and starts with new playgrounds at our Briarwood, Brookview and Seneca elementary schools. New and updated equipment will be installed, and similar playground work is scheduled for 2020 at Colebrook, Listwood and Southlawn, our other K-3 schools.
  • Closing date: Briarwood, Brookview and Seneca playgrounds will close Thursday, June 27, 2019.
  • Scheduled reopen: August 2019.
  • This fall: Roof work at Irondequoit HS. More on that soon.
  • Playground construction: Click on the school name below to see a picture of the “future” playground and also a map during construction.

We appreciate your understanding of the necessary work that needs to be done. Please contact our Office of Public Information at (585) 336-3067 with questions or concerns. Thank you! 